Back to articles

Longer-Term projects estimation

Estimating the time and resources required for long-term projects is a complex task, especially when using traditional estimation methods. These methods often fall short in capturing the dynamic and evolving nature of lengthy projects. To address this, many teams are turning to alternative estimation scales using weekly metrics. This approach provides greater flexibility and accuracy, allowing for more effective project management. Here are some key alternative estimation scales that can be employed for longer-term projects using weekly intervals:

T-Shirt Sizing

T-shirt sizing is a popular estimation technique that categorizes tasks or features into sizes like Small (S), Medium (M), Large (L), and Extra-Large (XL). For longer-term projects, each size can be mapped to a range of weeks:

  • Small (S): 1-2 weeks

  • Medium (M): 3-5 weeks

  • Large (L): 6-9 weeks

  • Extra-Large (XL): 10+ weeks

This approach simplifies the estimation process by providing broad time frames, making it easier to plan and allocate resources over extended periods.

Fibonacci Sequence

The Fibonacci sequence (1, 2, 3, 5, 8, 13, etc.) is another common estimation method used in Agile. For long-term projects, this sequence can be adapted to represent weeks:

  • 1: 1 week

  • 2: 2 weeks

  • 3: 3 weeks

  • 5: 5 weeks

  • 8: 8 weeks

  • 13: 13 weeks

By using Fibonacci numbers, teams can estimate the relative effort required for tasks, with larger numbers indicating more complex or time-consuming tasks. This method helps in prioritizing and planning work more effectively over longer timeframes.

Planning poker with Weeks

Planning Poker is a collaborative estimation technique where team members use cards to assign effort estimates to tasks. For longer-term projects, the cards can represent weeks instead of story points or hours:

  • 1 week, 2 weeks, 4 weeks, 6 weeks, 8 weeks, etc.

This technique encourages team discussion and consensus, leading to more accurate and realistic estimates. It also helps in identifying any discrepancies or misunderstandings about the project scope early on.

Kanban with Weekly Intervals

Kanban is a visual workflow management method that can be adapted for long-term project estimation using weekly intervals. Tasks are moved across columns representing different stages of completion, with each task tagged with an estimated number of weeks:

  • Backlog: Tasks waiting to be started

  • In Progress: Tasks currently being worked on, with weekly estimates

  • Review: Tasks under review, tagged with time spent

  • Done: Completed tasks, with actual time recorded

Using weekly intervals in Kanban helps teams monitor progress, identify bottlenecks, and adjust estimates based on real-time data.

Three-Point Estimation

Three-Point Estimation involves making three estimates for each task: optimistic (O), pessimistic (P), and most likely (M). For longer-term projects, these estimates can be in weeks:

  • Optimistic (O): Best-case scenario in weeks

  • Pessimistic (P): Worst-case scenario in weeks

  • Most Likely (M): Most probable scenario in weeks

This method provides a more balanced and comprehensive estimation by considering uncertainty and variability in project tasks.